Dominion Energy Hits Milestone in Coastal Virginia Offshore Wind Construction With the Installation of the 50th Monopile Foundation
Dominion Energy(D) Prnewswire·2024-08-12 22:15
Dominion Energy remains on target to install between 70-100 monopile foundations by end of October Coastal Virginia Offshore Wind remains on budget and on schedule to complete construction in late 2026 RICHMOND, Va., Aug. 12, 2024 /PRNewswire/ -- Dominion Energy announced today the 50th monopile foundation for the 2.6-gigawatt Coastal Virginia Offshore Wind (CVOW) was installed 33 miles off the coast of Virginia Beach, keeping the project on schedule to hit the company's target of 70-100 monopiles set into ...