Mining commences at Kiniéro as project tracks towards first gold in Q4 CY2025
Globenewswire·2025-10-16 19:00

Figure 11: Figure 11: Power station with engine haul building erected and switch room complete (12 October 2025) Figure 12: Figure 12: Sabali south pit grade control drilling (12 October 2025) Figure 13: Figure 13: Overland piping installation (12 October 2025) Highlights: Robex’s Kiniero Gold Project, Guinea, remains on track and budget for first gold pour in Q4 CY25. The Kiniero project remains LTI free (lost time injury) with 4,857,704 hours complete to 30 September 2025.Mine development act ...