Montage Gold Reports on its Q3-2025 Activities
Globenewswire·2025-11-13 06:15

Koné project construction on-budget and well on-schedule • Strong continued exploration focus • Robust liquidity sources CONSTRUCTION ACTIVITIES Rapid progress achieved with already +5.7 million hours worked with more than 2,900 employees and contractors on-siteWell on track for first gold pour in Q2-2027 and on budget with $494.8 million of capital committed as at today, representing approximately 58% of the total capital expenditure, with prices in line with expectationsKey process plant achievements incl ...