Quarterly Activities Report March 2026
Accessnewswire·2026-04-28 08:20
Quarterly Activities Report March 2026 Back to the Newsroom Quarterly Activities Report March 2026 Highlights Phase 1 construction at Hombre Muerto West (HMW) completed, a key inflection point as Galan transitions from developer to producer Plant electrical and mechanical systems testing complete, wet commissioning phase to commence soon A$40 million institutional placement completed at A$0.41 per share to fund the Phase 1 capacity expansion from 4 ktpa LCE to 5.2 ktpa LCE, working capital and to fund explo ...