Mining commences at Kiniéro as project tracks towards first gold in Q4 CY2025
Globenewswire· 2025-10-16 19:00
Figure 11: Figure 11: Power station with engine haul building erected and switch room complete (12 October 2025) Figure 12: Figure 12: Sabali south pit grade control drilling (12 October 2025) Figure 13: Figure 13: Overland piping installation (12 October 2025) Highlights: Robex’s Kiniero Gold Project, Guinea, remains on track and budget for first gold pour in Q4 CY25. The Kiniero project remains LTI free (lost time injury) with 4,857,704 hours complete to 30 September 2025.Mine development act ...
Galan Lithium Limited HMW Project Update
Accessnewswire· 2025-09-10 21:00
项目进展 - 阿根廷HMW锂盐湖项目一期建设持续推进 现场关键路径工程进展顺利[1] - Pond 4的详细设计已完成 正在进行pond liners的采购和电气系统设计[1] - Authium纳米过滤厂在悉尼的车间内进行建设 通用设备组装即将开始[1] 技术验证 - 测试工作证实了优异的杂质分离效果[1] - 过滤元件成功通过压力测试[1]